

KZN DoT Holds Vukuzakhe Indaba
Despite the fact that our Vukuzakhe programme has performed
well over the past several years, we need to review our Vukuzakhe programme to
ensure that emerging contractors benefit from the current boom in the
construction sector, and from the new policy environment that government has
developed in support of broad based black economic empowerment.
Our departmental review of Vukuzakhe has taken the following
concerns into consideration:
When the Vukuzakhe programme first started contractors were restricted to the
construction and maintenance of our gravel road network. Today, largely through
the African Renaissance Roads Upgrading Programme (ARRUP), contractors are
gaining experience through constructing highly sophisticated blacktop roads,
bridges and drainage systems.
(Top) Vukuzakhe contractors engaged in the construction of
structures on the provincial road network
(Bottom Left) Upgrading of Gravel to Blacktop Road
(Bottom Right) Road Marking on completed Blacktop Road
Contractors are only too well aware of the fact that a
movement from gravel road to blacktop road contracts entails a shift from more
labour intensive methodologies to capital intensive methodologies. Plant
requirements for constructing blacktop roads are of a much higher order in terms
of value and sophistication than those required for gravel roads. So much so
that for an emerging contractor to compete effectively for contracts to
construct blacktop roads, he/she must have accumulated plant to the value of
some R4,6 million. If R4,6 million worth of plant were financed through bank
loans it would require a monthly instalment of R141 000.
Our Vukuzakhe programme was initiated when the construction
industry in South Africa was still in serious recession. During the recession
many of the very large companies either:
Today the construction sector in South Africa is booming. So
much so that the Johannesburg Stock Exchange Construction and Building Materials
Index has gained more than 63% over the past year. For the past several years
our construction sector has grown at a much faster rate than that of the South
African economy. None of us need reminding that we are only beginning to prepare
for the 2010 Soccer World Cup and that South Africa is bidding against Japan and
New Zealand to host the 2011 Rugby World Cup.
In KwaZulu-Natal an already booming construction industry
will be further boosted by projects such as the Dube Trade Port, the
construction of the King Shaka airport and the John Ross Highway. In less than
ten years therefore the construction sector in South Africa has moved from doom
to boom. We must obviously now plan for the future of our emerging contractors
within an industry that is attracting more and more influential role players.
In the first years of Vukuzakhe the Department provided
contracts within a closed database system. This limited the number of
contractors on the database and ensured that each company was well known to the
Department and that there was no fronting. The re-opening of the Vukuzakhe
database increased our register to almost 25 000 contractors. In recent years we
have become aware of some instances of fronting within Vukuzakhe. This was
raised at the 2005 Departmental Summit held at Ulundi earlier this year as an
issue that must be addressed urgently. The department will not tolerate fronting
on any of our programmes – it will be rooted out and the guilty parties will
be harshly dealt with.
On the question of allegations of corruption generally, ways
of separating corrupt activities from legally accepted practices are being
investigated. For example, the department will be re-looking at the policy
regarding the trading of public servants. We will ensure that our monitoring
systems improve qualitatively rather than quantitatively in order to ensure that
the targeted audiences do benefit from these programmes.
These then are some of the more compelling reasons that
challenge us to review our Vukuzakhe programme. In charting the way forward we
need to acknowledge that we are building on very solid foundations. There are
not many broad based black economic empowerment programmes in South Africa that
can boast the same record as Vukuzakhe.
Some of the achievements of our Vukuzakhe programme since
1998 include:
864 contractors have progressed from Stage 1a to Stage 1b;
319 contractors have progressed from Stage 1b to Stage 2;
113 contractors have progressed from Stage 2 to Stage 3;
and
35 contractors have progressed from Stage 3 to Stage 4.
-
Some of our Stage 4 contractors now get contracts from
other departments, often for considerable sums of money. For example, Mr
Zondi, of Zondi’s Construction, started as a Stage 2 contractor in 1999
doing road patching. Today, he has a contract to build a bridge for the
Ingwe local municipality worth R1,8 million.
- Two of our most successful contractors are women, namely Mrs T.P. Zondi of
Thatheni Construction and Mrs Irene Gangerdine of Salli’s Construction.
Indeed Mrs Gangerdine was one of our first women contractors in the
Vukuzakhe programme. In 1999, she started as a Stage 2 contractor with a job
worth R257 682. This year, she is a Stage 4 contractor who has just
completed an earthworks contract worth R3,2 million. Between 1999 and 2005
she successfully completed 10 contracts worth R9,08 million.

back
|